ift-ts:qa:status:2026q1-status-qa-desktop

Description

Collaborate with Status team to ensure that the Status Desktop app behaves as expected.
Add new automated tests to the existing e2e testing framework for new features.
Oversee testing strategy around releases.

Task List

Maintenance

  • fully qualified name: ift-ts:qa:status:2026q1-status-qa-desktop:maintenance
  • owner: nastya
  • status: in progress (75%)
  • start-date: 2026/01/01
  • end-date: 2026/03/31

Description

  • Ongoing maintenance of Status Desktop tests.
    This includes updating tests for changes in status, addressing regressions,
    investigating and resolving issues, and implementing minor improvements
    to the testing framework as needed.

Deliverables

Release Testing

  • fully qualified name: ift-ts:qa:status:2026q1-status-qa-desktop:release-testing
  • owner: nastya
  • status: not started
  • start-date: 2026/01/01
  • end-date: 2026/03/31

Description

  • Support Q1 releases with testing.

Deliverables

  • PRs / Issues

Privacy Mode

  • fully qualified name: ift-ts:qa:status:2026q1-status-qa-desktop:privacy-mode
  • owner: nastya
  • status: not started
  • start-date: 2026/01/01
  • end-date: 2026/03/31

Description

  • Support new Privacy Mode feature in tests.
  • Add new tests and update existing ones.

Deliverables

  • PRs / Issues

Dapp Browser

  • fully qualified name: ift-ts:qa:status:2026q1-status-qa-desktop:dapp-browser
  • owner: nastya
  • status: not started
  • start-date: 2026/01/01
  • end-date: 2026/03/31

Description

  • Support Browser feature in tests.
  • Add new tests and update existing ones.

Deliverables

  • PRs / Issues

Local Backup Opt-in

  • fully qualified name: ift-ts:qa:status:2026q1-status-qa-desktop:local-backup-opt-in
  • owner: nastya
  • status: not started
  • start-date: 2026/01/01
  • end-date: 2026/03/31

Description

  • Opt-in messages Local Backup feature support in tests.

Deliverables

  • PRs / Issues

External Activity

  • fully qualified name: ift-ts:qa:status:2026q1-status-qa-desktop:external-activity
  • owner: nastya
  • status: not started
  • start-date: 2026/01/01
  • end-date: 2026/03/31

Description

  • Support Activity fetching feature in tests.

Deliverables

  • PRs / Issues

Integrate Linea chain

  • fully qualified name: ift-ts:qa:status:2026q1-status-qa-desktop:linea-chain
  • owner: nastya
  • status: in progress (50%)
  • start-date: 2026/01/01
  • end-date: 2026/03/31

Description

  • Support Linea chain feature in tests.

Deliverables

Standardized approach for Popups / Menus / Dropdowns

  • fully qualified name: ift-ts:qa:status:2026q1-status-qa-desktop:standardized-approach
  • owner: nastya
  • status: not started
  • start-date: 2026/01/01
  • end-date: 2026/03/31

Description

  • Support Standardized approach for Popups / Menus / Dropdowns feature in tests.

Deliverables

  • PRs / Issues

Private Transactions POC

  • fully qualified name: ift-ts:qa:status:2026q1-status-qa-desktop:private-transactions
  • owner: nastya
  • status: not started
  • start-date: 2026/01/01
  • end-date: 2026/03/31

Description

  • Support Private Transactions POC feature in tests.

Deliverables

  • PRs / Issues

Activity Center & Notifications

  • fully qualified name: ift-ts:qa:status:2026q1-status-qa-desktop:activity-center-and-notifications
  • owner: nastya
  • status: not started
  • start-date: 2026/01/01
  • end-date: 2026/03/31

Description

  • Support Activity Center & Notifications – UX, Consistency and Responsive Improvements feature in tests.

Deliverables

  • PRs / Issues

Backup feature improvements

  • fully qualified name: ift-ts:qa:status:2026q1-status-qa-desktop:backup-improvements
  • owner: nastya
  • status: not started
  • start-date: 2026/01/01
  • end-date: 2026/03/31

Description

  • Support Backup feature improvements feature in tests.

Deliverables

  • PRs / Issues

Unified Adaptive Navigation System

  • fully qualified name: ift-ts:qa:status:2026q1-status-qa-desktop:unified-adaptive-navigation-system
  • owner: nastya
  • status: done
  • start-date: 2026/01/01
  • end-date: 2026/01/27

Description

  • Support Unified Adaptive Navigation System feature in tests.

Deliverables