vac:nim:waku:2026q1-waku-nimble-integration

Description

Support the Waku team as they integrate Nimble into Nwaku, troubleshoot and fix integration mismatches, and document gaps for follow-up.

Task List

Waku Nimble integration Support

  • fully qualified name: vac:nim:waku:2026q1-waku-nimble-integration:integration-support
  • owner: TBD
  • status: not started
  • start-date: 2026/01/01
  • end-date: 2026/02/10

Description

Support the Waku team with fixing issues that come up during their Nimble -> Waku integration efforts.

Deliverables

  • PRs/Issues/Docs/Reports

Complete Waku Nimble integration

  • fully qualified name: vac:nim:waku:2026q1-waku-nimble-integration:complete-integration
  • owner: TBD
  • status: not started
  • start-date: 2026/02/10
  • end-date: 2026/03/31

Description

Complete the integration of Nimble into Waku, if any tasks remain outstanding the Waku team did not complete yet.

Deliverables

  • PRs/Issues/Docs/Reports